Project simplified schedule

Project simplified schedule

 

The HiLumi life cycle is divided in 4 main phases. The procurement of components is launched between 6 and 18 month before the “Fabrication, Assembly & Verification phase”. The time will depend on the cost of the procurement reaching up to 18 month for supplies which value is higher than 750 KCHF. 

 